Restoring a little piece of Gravetye’s magic: The Summer House

Article by: 05/11/2026

There is something rather special about the gardens at Gravetye Manor. Originally created by William Robinson in 1885, they are now recognised as one of England’s most important historic gardens and remain a remarkable legacy of a man who fundamentally changed the way we think about gardening.

Robinson, affectionately remembered as the Irishman who taught the English how to garden, championed a more natural approach to planting. His influential books, The Wild Garden and The English Flower Garden, helped inspire generations to celebrate nature rather than try to control it.

Having bought Gravetye Manor in 1884, Robinson used the surrounding estate as a living expression of his ideas. Within the 35 acres surrounding the Manor, he created what is undoubtedly his garden masterpiece. Today, the garden team continues to care for this extraordinary landscape, building on the work of its original creator and ensuring that his vision lives on.

It is within this very special setting that the recent restoration of the Gravetye Manor Summer House took place – a small building with a rather important place in the history and character of the gardens.

A favourite spot, restored

Built by William Robinson in 1902, the Summer House occupies what was apparently his favourite spot at Gravetye. Measuring just 4.2m by 4.2m, it is a beautiful example of traditional craftsmanship, with an oak timber frame, Sussex sandstone walls, oak featheredge boarding and a Horsham stone slate roof, finished with an elegant lead finial.

But after more than 120 years exposed to the elements, the

The hidden drain

building was in considerable need of attention. The timber frame had deteriorated, the stonework had shifted and the roof had gradually pulled the structure out of alignment. Poor drainage, including an old drain hidden beneath a substantial vine root system, had contributed to the movement. Added to which it looks as though the structure was built 75mm out of level from south to north in the first place, and over the last 124 years it has drifted another 75mm.

 

The challenge was to restore the building without dismantling it, retaining as much of the original fabric and character as possible.  This was taken on by JP Heritage Construction, led by multi-award winning John Zielinski, working alongside his brother Matthew .  The spec and conservation plans were undertaken by Neil England of HBA.

Traditional craftsmanship and some clever problem-solving

The stonework presented one of the first challenges. A section of the southeast wall had sunk by around 65mm, and lifting it proved considerably harder than anticipated – the wall

Cranking it back

carried on another 600mm below ground and was one solid mass. Even a car jack gave up! The team eventually used large steel wedges, shims and a long lever to ease the substantial stone wall slowly back into position.

The gaps were then carefully packed using stainless steel shims and NHL 3.5 lime mortar. To achieve a sympathetic finish, the team created their own mortar, and to finish, they crushed some Sussex sandstone to dust, added ash powder and mixed it with quicklime to make a stone-coloured mortar that ‘fakes’ the look of stone. It now looks as though new stone has been set in under the wall, which sits back in its original position.

The repointing to the buttress and other areas was done in a similar way. Using quicklime,

The test biscuits

ash and crushed stone, the team took their time and made up test biscuits to match every new mortar before it went on. That gave them a close, if not exact, match wherever they repointed.

The Timber Frame

The sole plate had rotted out on every flank, to the point where the building was becoming unstable. Over 124 years the weather had really taken its toll. The roof had ‘sailed’ over and was pulling the building almost 100mm out of plumb, and most of the tenons on the south flank had rotted away completely.

Removing the old posts

Finding replacement oak of the required size was no easy task, and timber had to be brought over from France.

The brief was to replace the sole plate without taking the structure down. They set props in strategic positions and started by lifting the north flank. At the same time they were able to push the roof back over by around 40mm to straighten up the lean. Flank by flank, they lifted the whole structure by around 60mm, stabilising it with blocks and folding wedges as they went. That 60mm let them remove the old sole plate and still leave at least a 50 to 60mm tenon to go into the new one. Long hex bolts then tied everything together and stabilised the frame.

New posts in place

In a lovely example of making the most of what was already there, the old oak posts were milled down and reused to make the new glazing beads and trenails. Once the structural work was complete, the building was carefully lowered back into position, with the internal timbers finished in black stain to match their original appearance.

Protecting more than just a building

The result is a beautifully restored Summer House, with a new lease of life and the prospect of another 60 to 100 years of service.

But the importance of this project goes well beyond the restoration of a charming garden building.

The Zielinski brothers at the finished Summer House

The Summer House is not simply part of the visitor experience at Gravetye Manor, nor is its significance measured by the number of hotel guests who might enjoy it. It is part of the magic that William Robinson created here. It belongs to the story of the gardens, to the landscape he shaped and to the extraordinary legacy he left behind.

The Summer House is a wonderful example of how sensitive restoration, traditional materials and skilled craftsmanship can secure the future of our heritage without losing the qualities that make it special in the first place.